On July 30, 2024, PJM's capacity price rose 9.3 times in a single auction, and the release did not mention data centres once. Two years later the cause was harder to leave out. The case tests the global climate worry first and finds it does not hold, then follows the cost to where it lands: Ireland, where data centres take more electricity than every city home; Virginia, where a household bill could rise $14 to $37 a month by 2040; the PJM grid, where $23.1 billion of capacity revenue traces to data centres; and Memphis and Southaven, where gas turbines ran without air permits. It asks who should pay for the waiting.

The question
Since December 2025 a new data centre in Ireland must bring dispatchable power matching its own demand before it connects, and PJM's December 2026 auction was the first to leave new large loads out. Should a new data centre have to bring its own power?
In brief
The global climate case does not hold. Data centres used about 1.5% of world electricity in 2024, heading for about 3% by 2030; the EPA's 2007 extrapolation of this curve overshot by 40% to 65%.
The cost lands on four addresses. Ireland (23% of metered electricity), Virginia ($14 to $37 a month on a household bill by 2040), PJM ($23.1 billion of capacity revenue) and Memphis and Southaven (turbines without air permits).
Most announced megawatts will not be built. 189 GW of gas is in development for US data centres, against 6.3 GW of gas of all kinds coming online in 2026.
What I would have built. A firm-commitment gate before any load enters a forecast, and disclosure of marginal emissions and consumed water; who absorbs the cost stays a human call.